Action Date | Action Description |
---|---|
Apr 19, 2024 | Assent Application Received |
Apr 24, 2024 | Administrative Review for Completeness |
Apr 24, 2024 | Bio Team Review for Completeness |
Apr 24, 2024 | Project Manager |
Apr 24, 2024 | Application Accepted |
May 24, 2024 | Additional Information Received |
May 27, 2024 | HPHC Historical Preservation No Effect |
Jun 18, 2024 | Biologist Report |
Jun 28, 2024 | Typist for Processing |
Jun 28, 2024 | Executive Sign Off |
Jun 28, 2024 | Sent to Photo Copy |
Jun 28, 2024 | Permit Approved |
Jul 02, 2024 | Permit Mailed |
Sep 27, 2024 | Commencement of Work Notice received |
Oct 08, 2024 | Land Evidence Date |