Action Date | Action Description |
---|---|
Oct 14, 1976 | Application Accepted |
Dec 17, 1976 | Permit Approved |
Jun 15, 2005 | Modification Request |
Jun 17, 2005 | Administrative Review for Completeness |
Jun 20, 2005 | Team Review for Completeness |
Jul 12, 2005 | Additional Information Received |
Jul 14, 2005 | Historical Preservation Approval Granted |
Aug 03, 2005 | 30 day Public Notice Issued |
Sep 03, 2005 | Public Notice End Date |
Sep 14, 2005 | Additional Information Received |
Sep 15, 2005 | US Army Corp of Engineers Permit Date |
Sep 16, 2005 | Biologist Report |
Sep 16, 2005 | Engineering Report |
Sep 19, 2005 | US Army Corps of Engineers Approval Received |
Sep 19, 2005 | Supervisor Biologist SignOff |
Sep 19, 2005 | Supervisor Engineer SignOff |
Sep 21, 2005 | Executive Sign Off |
Oct 05, 2005 | Ready to Schedule Semi-Monthly Meeting |
Oct 05, 2005 | Mail Agenda Notice |
Oct 07, 2005 | Continued Application by the Council |
Oct 19, 2005 | Mail Agenda Notice |
Oct 25, 2005 | Semi-Monthly Meeting Held |
Oct 25, 2005 | Council Approval Granted |
Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled |
Oct 31, 2005 | Stipulation Package from Biologist |
Oct 31, 2005 | Stipulation Package by Engineer |
Oct 31, 2005 | Typist for Processing |
Oct 31, 2005 | Executive Sign Off |
Oct 31, 2005 | Sent to Photo Copy |
Oct 31, 2005 | Modification Approved |
Nov 05, 2005 | Land Evidence Date |
Dec 02, 2005 | Legal Response/Decision |