Action Date | Action Description |
---|---|
Dec 01, 2003 | Application Accepted |
Dec 01, 2003 | Category M assigned |
Dec 10, 2003 | Historical Preservation Approval Granted |
Dec 12, 2003 | Objections/Comments Received |
Sep 14, 2004 | Biologist Report |
Sep 16, 2004 | Typist for Processing |
Feb 15, 2005 | Correspondence Received |
Jun 20, 2005 | Correspondence Received |
Aug 18, 2005 | Ready to Schedule Semi-Monthly Meeting |
Aug 18, 2005 | Mail Agenda Notice |
Aug 23, 2005 | Semi-Monthly Meeting Held |
Aug 23, 2005 | Council Approval Granted |
Aug 23, 2005 | Semi-Monthly Meeting Date Scheduled |
Sep 15, 2005 | Assent Amended |
Sep 15, 2005 | Land Evidence Date |
Sep 20, 2005 | Executive Sign Off |
Sep 21, 2005 | Executive Sign Off |
Sep 21, 2005 | Legal Response/Decision |
Oct 24, 2005 | Biologist Report |
Oct 16, 2006 | Modification Request |
Oct 17, 2006 | Administrative Review for Completeness |
Oct 19, 2006 | Deficient Application - Owner Notification Sent |
Oct 30, 2006 | Deficient Application Picked Up |
Dec 11, 2006 | Modification Request |
Dec 12, 2006 | Administrative Review for Completeness |
Dec 12, 2006 | Team Review for Completeness |
Dec 12, 2006 | Team Review for Completeness |
Dec 19, 2006 | HPHC Historical Preservation No Effect |
Dec 26, 2006 | 30 day Public Notice Issued |
Jan 23, 2007 | Objections/Comments Received |
Jan 23, 2007 | Correspondence Mailed/Faxed/E-mailed |
Jan 26, 2007 | Public Notice End Date |
Mar 26, 2007 | US Army Corp of Engineers Permit Date |
Mar 28, 2007 | US Army Corps of Engineers Approval Received |
Oct 17, 2007 | 30-Day Notification of Cancellation letter |
Oct 19, 2007 | Certified Receipt Received |
Aug 19, 2010 | 30-Day Notification of Cancellation letter |
Aug 19, 2010 | Additional Information Requested from Applicant |
Aug 27, 2010 | Certified Receipt Received |
Dec 04, 2013 | Additional Information Requested from Applicant |
Mar 16, 2015 | Modification Request |
Mar 16, 2015 | Biologist Report |
Mar 19, 2015 | Administrative Review for Completeness |
Mar 31, 2015 | Team Review for Completeness |
Apr 13, 2015 | Biologist Report |
Apr 16, 2015 | Typist for Processing |
Apr 16, 2015 | Executive Sign Off |
Apr 20, 2015 | Modification Approved |