Action Date | Action Description |
---|---|
Jun 03, 2008 | Assent Application Received |
Jun 04, 2008 | Administrative Review for Completeness |
Jun 05, 2008 | Team Review for Completeness |
Jun 05, 2008 | Team Review for Completeness |
Jun 10, 2008 | Deficient Application - Owner Notification Sent |
Jun 11, 2008 | Deficiency Response Received |
Jun 27, 2008 | Additional Information Received |
Jun 27, 2008 | Team Review for Completeness |
Jun 27, 2008 | Application Accepted |
Aug 01, 2008 | HPHC Historical Preservation No Effect |
Apr 14, 2009 | Engineering Report |
Apr 14, 2009 | Biologist Report |
Apr 15, 2009 | Supervisor Biologist SignOff |
Apr 15, 2009 | Supervisor Engineer SignOff |
Apr 27, 2009 | Executive Signoff of Staff Reports |
Oct 14, 2009 | Ready to Schedule Semi-Monthly Meeting |
Oct 14, 2009 | Mail Agenda Notice |
Oct 21, 2009 | Semi-Monthly Meeting Date Scheduled |
Nov 30, 2009 | Mail Agenda Notice |
Dec 08, 2009 | Semi-Monthly Meeting Date Scheduled |
Dec 08, 2009 | Remanded back to staff by Council |
Mar 05, 2010 | Plans Received |
Mar 19, 2010 | Additional Information Received |
Mar 23, 2010 | Engineering Report |
Mar 23, 2010 | Biologist Report |
Mar 24, 2010 | Permit Approved |
Apr 13, 2010 | Land Evidence Date |
Sep 29, 2010 | Commencement of Work Notice received |