Action Date | Action Description |
---|---|
Sep 05, 2008 | Assent Application Received |
Sep 08, 2008 | Administrative Review for Completeness |
Sep 11, 2008 | Team Review for Completeness |
Sep 11, 2008 | Team Review for Completeness |
Sep 11, 2008 | Deficient Application - Owner Notification Sent |
Sep 16, 2008 | Deficient Application Picked Up |
Sep 26, 2008 | Deficiency Response Received |
Oct 01, 2008 | Administrative Review for Completeness |
Oct 01, 2008 | Team Review for Completeness |
Oct 01, 2008 | Team Review for Completeness |
Oct 01, 2008 | Application Accepted |
Oct 21, 2008 | HPHC Historical Preservation No Effect |
Oct 30, 2008 | Biologist Report |
Oct 30, 2008 | Engineering Report |
Nov 03, 2008 | Typist for Processing |
Nov 03, 2008 | Executive Sign Off |
Nov 03, 2008 | Sent to Photo Copy |
Nov 03, 2008 | Permit Approved |
Dec 02, 2008 | Land Evidence Date |