Action Date | Action Description |
---|---|
Feb 06, 2009 | Assent Application Received |
Feb 09, 2009 | Administrative Review for Completeness |
Feb 09, 2009 | Team Review for Completeness |
Feb 09, 2009 | Team Review for Completeness |
Feb 09, 2009 | Application Accepted |
Mar 25, 2009 | Plans Received |
Mar 31, 2009 | HPHC Historical Preservation No Effect |
Apr 07, 2009 | Plans Received |
Apr 10, 2009 | Typist for Processing |
Apr 10, 2009 | Executive Sign Off |
Apr 10, 2009 | Sent to Photo Copy |
Apr 10, 2009 | Permit Approved |
Apr 10, 2009 | Biologist Report |
Apr 10, 2009 | Engineering Report |
May 01, 2009 | Land Evidence Date |
Nov 30, 2017 | Modification Request |
Dec 01, 2017 | Administrative Review for Completeness |
Dec 01, 2017 | Team Review for Completeness |
Dec 01, 2017 | Application Accepted |
Dec 07, 2017 | Biologist Report |
Dec 08, 2017 | Typist for Processing |
Dec 08, 2017 | Executive Sign Off |
Dec 08, 2017 | Sent to Photo Copy |
Dec 08, 2017 | Modification Approved |
Feb 28, 2018 | Land Evidence Date |
Jun 21, 2018 | HPHC Historical Preservation No Effect |