Action Date | Action Description |
---|---|
Oct 05, 2009 | Assent Application Received |
Oct 05, 2009 | Administrative Review for Completeness |
Oct 06, 2009 | Team Review for Completeness |
Oct 06, 2009 | Team Review for Completeness |
Oct 06, 2009 | Application Accepted |
Nov 09, 2009 | HPHC Historical Preservation No Effect |
Nov 24, 2009 | 30 day Public Notice Issued |
Dec 18, 2009 | Correspondence Received |
Dec 24, 2009 | Public Notice End Date |
Jan 12, 2010 | Biologist Report |
Jan 12, 2010 | Engineering Report |
Jan 13, 2010 | Typist for Processing |
Jan 13, 2010 | Permit Approved |
Jan 13, 2010 | Executive Sign Off |
Jan 13, 2010 | Sent to Photo Copy |
Jun 22, 2010 | Duplicate Original Assent requested/mailed |
Jun 28, 2010 | Land Evidence Date |