Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 15, 2009 | Assent Application Received |
Oct 16, 2009 | Administrative Review for Completeness |
Oct 30, 2009 | Team Review for Completeness |
Oct 30, 2009 | Team Review for Completeness |
Oct 30, 2009 | Deficient Application - Owner Notification Sent |
Nov 30, 2009 | Deficiency Response Received |
Dec 07, 2009 | Team Review for Completeness |
Dec 07, 2009 | Team Review for Completeness |
Dec 07, 2009 | Application Accepted |
Dec 07, 2009 | Category A* (Docks) |
Dec 17, 2009 | HPHC Historical Preservation No Effect |
Jan 07, 2010 | 30 day Public Notice Issued |
Feb 07, 2010 | Public Notice End Date |
Mar 12, 2010 | Public Notice End Date Extension Granted |
May 20, 2010 | US Army Corp of Engineers Permit Date |
Jun 01, 2010 | US Army Corps of Engineers Approval Received |
Jun 02, 2010 | Biologist Report |
Jun 02, 2010 | Engineering Report |
Jun 03, 2010 | Permit Approved |
Jun 22, 2010 | Land Evidence Date |
Jan 07, 2015 | Modification Request |
Jan 07, 2015 | Administrative Review for Completeness |
Jan 14, 2015 | Team Review for Completeness |
Jan 21, 2015 | Deficient Application - Owner Notification Sent |
Feb 04, 2015 | Deficient Application Picked Up |
Apr 16, 2019 | Modification Request |
Apr 16, 2019 | Administrative Review for Completeness |
Apr 23, 2019 | Team Review for Completeness |
Apr 23, 2019 | Application Accepted |
May 10, 2019 | HPHC Historical Preservation No Effect |
May 10, 2019 | HPHC Review Pending |
Jun 17, 2019 | 30 day Public Notice Issued |
Jul 09, 2019 | Letter of Support for Project |
Jul 17, 2019 | Public Notice End Date |
Jul 22, 2019 | Letter of Support for Project |
Jul 29, 2019 | Dock/1.1.6 Review approval |
Aug 05, 2019 | Biologist Report |
Aug 06, 2019 | Modification Approved |
Aug 21, 2019 | Land Evidence Date |