Oct 26, 2009 | Maintenance Certification Request |
Oct 26, 2009 | Administrative Review for Completeness |
Oct 27, 2009 | Team Review for Completeness |
Oct 30, 2009 | Team Review for Completeness |
Oct 30, 2009 | Plans Received |
Oct 30, 2009 | Application Accepted |
Oct 30, 2009 | Biologist Report |
Oct 30, 2009 | Engineering Report |
Oct 30, 2009 | Typist for Processing |
Oct 30, 2009 | Permit Approved |
Nov 02, 2009 | Executive Sign Off |
Nov 02, 2009 | Sent to Photo Copy |
Nov 30, 2009 | Land Evidence Date |
Dec 01, 2009 | US Army Corps of Engineers Approval Received |
Sep 24, 2010 | Entry of Appearance Received |
Oct 28, 2011 | Modification Request |
Nov 02, 2011 | Administrative Review for Completeness |
Nov 03, 2011 | Team Review for Completeness |
Nov 03, 2011 | Team Review for Completeness |
Nov 30, 2011 | HPHC Historical Preservation No Effect |
Dec 29, 2011 | Plans Received |
Dec 29, 2011 | Typist for Processing |
Dec 29, 2011 | Modification Approved |
Dec 29, 2011 | Biologist Report |
Dec 29, 2011 | Engineering Report |
Dec 30, 2011 | Executive Sign Off |
Dec 30, 2011 | Sent to Photo Copy |
Jan 20, 2012 | Land Evidence Date |
May 29, 2012 | Modification Request |
May 31, 2012 | Administrative Review for Completeness |
Jun 06, 2012 | Team Review for Completeness |
Jun 06, 2012 | Team Review for Completeness |
Jun 07, 2012 | Biologist Report |
Jun 07, 2012 | Engineering Report |
Jun 11, 2012 | Typist for Processing |
Jun 11, 2012 | Executive Sign Off |
Jun 11, 2012 | Sent to Photo Copy |
Jun 11, 2012 | Modification Approved |
Jun 12, 2012 | HPHC Historical Preservation No Effect |
Jan 28, 2013 | Land Evidence Date |