Action Date | Action Description |
---|---|
Oct 26, 2009 | Assent Application Received |
Oct 26, 2009 | Administrative Review for Completeness |
Oct 30, 2009 | Team Review for Completeness |
Oct 30, 2009 | Team Review for Completeness |
Oct 30, 2009 | Deficient Application - Owner Notification Sent |
Dec 17, 2009 | Deficiency Response Received |
Jan 05, 2010 | Team Review for Completeness |
Jan 05, 2010 | Team Review for Completeness |
Jan 05, 2010 | Application Accepted |
Jan 31, 2010 | HPHC Historical Preservation No Effect |
May 05, 2010 | Additional Information Requested from Applicant |
May 26, 2010 | Correspondence Received |
Jun 10, 2010 | Additional Information Received |
Jul 07, 2010 | Additional Information Received |
Jul 15, 2010 | Additional Information Received |
Dec 09, 2010 | Additional Information Requested from Applicant |
Dec 25, 2010 | Correspondence Received |
Dec 25, 2010 | Correspondence Received |
Feb 08, 2011 | Correspondence Received |
Feb 08, 2011 | Correspondence Received |
May 12, 2011 | Additional Information Received |
May 23, 2011 | 30 day Public Notice Issued |
Jun 13, 2011 | Additional Information Received |
Jun 13, 2011 | Plans Received |
Jun 15, 2011 | 30 day Public Notice Issued |
Jun 23, 2011 | Public Notice End Date |
Aug 11, 2011 | Correspondence Received |
Sep 27, 2011 | Biologist Report |
Sep 27, 2011 | Engineering Report |
Oct 07, 2011 | Supervisor Engineer SignOff |
Oct 07, 2011 | Supervisor Biologist SignOff |
Oct 11, 2011 | Executive Signoff of Staff Reports |
Oct 11, 2011 | Mail Agenda Notice |
Oct 20, 2011 | Additional Information Received |
Oct 25, 2011 | Semi-Monthly Meeting Held |
Oct 25, 2011 | Semi-Monthly Meeting Date Scheduled |
Jan 03, 2012 | Legal Response/Decision |
Jun 04, 2012 | Additional Information Received |