Action Date | Action Description |
---|---|
Oct 29, 2009 | Assent Application Received |
Oct 30, 2009 | Administrative Review for Completeness |
Nov 03, 2009 | Team Review for Completeness |
Nov 03, 2009 | Team Review for Completeness |
Nov 03, 2009 | Application Accepted |
Nov 03, 2009 | Category A* (Docks) |
Nov 16, 2009 | 30 day Public Notice Issued |
Dec 11, 2009 | HPHC Historical Preservation No Effect |
Dec 16, 2009 | Public Notice End Date |
Dec 18, 2009 | Correspondence Received |
Dec 23, 2009 | Public Notice End Date Extension Granted |
Jan 12, 2010 | Additional Information Received |
Jan 26, 2010 | US Army Corp of Engineers Permit Date |
Feb 01, 2010 | US Army Corps of Engineers Approval Received |
Feb 11, 2010 | Dock Meeting -- Approval |
Feb 12, 2010 | Biologist Report |
Feb 12, 2010 | Engineering Report |
Feb 15, 2010 | Typist for Processing |
Feb 15, 2010 | Executive Sign Off |
Feb 15, 2010 | Sent to Photo Copy |
Feb 15, 2010 | Permit Approved |
Feb 24, 2010 | Land Evidence Date |
Jun 07, 2010 | Commencement of Work Notice received |