Action Date | Action Description |
---|---|
Nov 02, 2009 | Assent Application Received |
Nov 03, 2009 | Administrative Review for Completeness |
Nov 04, 2009 | Team Review for Completeness |
Nov 04, 2009 | Team Review for Completeness |
Nov 04, 2009 | Application Accepted |
Nov 04, 2009 | Category A* (Docks) |
Nov 04, 2009 | 30 day Public Notice Issued |
Nov 09, 2009 | HPHC Historical Preservation No Effect |
Dec 04, 2009 | Public Notice End Date |
Jan 06, 2010 | Dock Meeting -- Approval |
Jan 06, 2010 | Typist for Processing |
Jan 06, 2010 | Permit Approved |
Jan 06, 2010 | Biologist Report |
Jan 06, 2010 | Engineering Report |
Jan 13, 2010 | Commencement of Work Notice received |
Mar 01, 2010 | Land Evidence Date |
May 13, 2011 | Modification Request |
May 16, 2011 | Administrative Review for Completeness |
May 16, 2011 | Team Review for Completeness |
May 16, 2011 | Team Review for Completeness |
May 24, 2011 | HPHC Historical Preservation No Effect |
May 26, 2011 | Biologist Report |
May 26, 2011 | Engineering Report |
Jun 02, 2011 | Typist for Processing |
Jun 02, 2011 | Modification Approved |
Jun 03, 2011 | Executive Sign Off |
Jun 03, 2011 | Sent to Photo Copy |
Jun 13, 2011 | Land Evidence Date |