Action Date | Action Description |
---|---|
Nov 03, 2009 | Maintenance Certification Request |
Nov 04, 2009 | Administrative Review for Completeness |
Nov 05, 2009 | Team Review for Completeness |
Nov 05, 2009 | Team Review for Completeness |
Nov 05, 2009 | Application Accepted |
Nov 09, 2009 | Additional Information Received |
Nov 12, 2009 | HPHC Historical Preservation No Effect |
Nov 12, 2009 | Biologist Report |
Nov 12, 2009 | Engineering Report |
Nov 13, 2009 | Typist for Processing |
Nov 13, 2009 | Permit Approved |