Action Date | Action Description |
---|---|
Jan 29, 2010 | Assent Application Received |
Feb 01, 2010 | Administrative Review for Completeness |
Feb 02, 2010 | Team Review for Completeness |
Feb 12, 2010 | Team Review for Completeness |
Feb 16, 2010 | Deficient Application - Owner Notification Sent |
Mar 08, 2010 | Deficiency Response Received |
Mar 16, 2010 | Team Review for Completeness |
Mar 16, 2010 | Team Review for Completeness |
Mar 16, 2010 | Application Accepted |
Apr 16, 2010 | HPHC Historical Preservation No Effect |
Apr 30, 2010 | Additional Information Received |
May 04, 2010 | Engineering Report |
May 05, 2010 | Biologist Report |
May 07, 2010 | Permit Approved |
May 28, 2010 | Land Evidence Date |