Action Date | Action Description |
---|---|
Feb 10, 2010 | Assent Application Received |
Feb 10, 2010 | Administrative Review for Completeness |
Feb 11, 2010 | Team Review for Completeness |
Feb 12, 2010 | Team Review for Completeness |
Feb 16, 2010 | Deficient Application - Owner Notification Sent |
Feb 23, 2010 | Deficient Application Picked Up |
Apr 07, 2010 | Deficiency Response Received |
Apr 08, 2010 | Team Review for Completeness |
Apr 08, 2010 | Application Accepted |
May 17, 2010 | HPHC Historical Preservation No Effect |
Jun 04, 2010 | Permit Approved |
Jun 04, 2010 | Biologist Report |
Jun 17, 2010 | Land Evidence Date |
Nov 03, 2010 | Commencement of Work Notice received |