Action Date | Action Description |
---|---|
Feb 16, 2010 | Assent Application Received |
Feb 17, 2010 | Administrative Review for Completeness |
Feb 17, 2010 | Team Review for Completeness |
Feb 17, 2010 | Team Review for Completeness |
Feb 17, 2010 | Deficient Application Picked Up |
Jun 08, 2010 | Deficiency Response Received |
Jun 08, 2010 | Team Review for Completeness |
Jun 11, 2010 | Application Accepted |
Jun 11, 2010 | Team Review for Completeness |
Jun 15, 2010 | Additional Information Received |
Jun 18, 2010 | HPHC Historical Preservation No Effect |
Jun 30, 2010 | Additional Information Received |
Jul 20, 2010 | Plans Received |
Jul 21, 2010 | 30 day Public Notice Issued |
Aug 11, 2010 | Correspondence Received |
Aug 21, 2010 | Public Notice End Date |
Sep 21, 2010 | Biologist Report |
Sep 21, 2010 | Engineering Report |
Sep 23, 2010 | Category A* (Docks) |
Sep 23, 2010 | Typist for Processing |
Sep 23, 2010 | Permit Approved |
Sep 24, 2010 | Executive Sign Off |
Sep 24, 2010 | Sent to Photo Copy |
Sep 28, 2010 | US Army Corp of Engineers Permit Date |
Oct 01, 2010 | Land Evidence Date |