Action Date | Action Description |
---|---|
Feb 22, 2010 | Assent Application Received |
Feb 23, 2010 | Administrative Review for Completeness |
Feb 23, 2010 | Team Review for Completeness |
Feb 25, 2010 | Deficient Application - Owner Notification Sent |
Mar 22, 2010 | Deficient Application Picked Up |
Nov 23, 2010 | Deficiency Response Received |
Nov 30, 2010 | Team Review for Completeness |
Nov 30, 2010 | Application Accepted |
Dec 09, 2010 | HPHC Historical Preservation No Effect |
Dec 17, 2010 | Additional Information Received |
Jan 20, 2011 | Biologist Report |
Jan 26, 2011 | Typist for Processing |
Jan 26, 2011 | Permit Approved |
Jan 28, 2011 | Executive Sign Off |
Jan 28, 2011 | Sent to Photo Copy |
Feb 04, 2011 | Land Evidence Date |