Action Date | Action Description |
---|---|
Feb 22, 2010 | Assent Application Received |
Feb 23, 2010 | Administrative Review for Completeness |
Feb 25, 2010 | Team Review for Completeness |
Feb 25, 2010 | Team Review for Completeness |
Feb 25, 2010 | Application Accepted |
Mar 04, 2010 | HPHC Historical Preservation No Effect |
Aug 26, 2010 | Additional Information Received |
Oct 21, 2010 | Biologist Report |
Oct 21, 2010 | Engineering Report |
Oct 26, 2010 | Typist for Processing |
Oct 26, 2010 | Permit Approved |
Oct 28, 2010 | Executive Sign Off |
Oct 28, 2010 | Sent to Photo Copy |
Dec 01, 2010 | Land Evidence Date |
Mar 11, 2014 | Extension Toll letter mailed |
Aug 18, 2014 | Phone Call |