Action Date | Action Description |
---|---|
Mar 03, 2010 | Assent Application Received |
Mar 04, 2010 | Administrative Review for Completeness |
Mar 04, 2010 | Team Review for Completeness |
Mar 04, 2010 | Team Review for Completeness |
Mar 04, 2010 | Application Accepted |
Mar 11, 2010 | 30 day Public Notice Issued |
Mar 25, 2010 | HPHC Historical Preservation No Effect |
Apr 07, 2010 | Objections/Comments Received |
Apr 09, 2010 | Objections/Comments Received |
Apr 11, 2010 | Public Notice End Date |
Apr 16, 2010 | Entry of Appearance Received |
Jun 21, 2010 | Entry of Appearance Received |
Sep 16, 2010 | Correspondence Received |
Feb 13, 2012 | Biologist Report |
Feb 13, 2012 | Engineering Report |
Feb 16, 2012 | Additional Information Received |
Mar 20, 2012 | Supervisor Engineer SignOff |
Mar 21, 2012 | Supervisor Biologist SignOff |
Aug 07, 2012 | Ready to Schedule Semi-Monthly Meeting |
Aug 09, 2012 | Mail Agenda Notice |
Aug 14, 2012 | Continuance Requested |
Aug 16, 2012 | Continuance request by applicant granted by Director |
Aug 28, 2012 | Semi-Monthly Meeting Date Scheduled |
Oct 24, 2012 | Ready to Schedule Semi-Monthly Meeting |
Oct 24, 2012 | Mail Agenda Notice |
Oct 31, 2012 | Continuance Requested |
Nov 09, 2012 | Continuance request by applicant granted by Director |
Nov 13, 2012 | Semi-Monthly Meeting Date Scheduled |
Sep 17, 2014 | 30-Day Notification of Cancellation letter |
Jan 06, 2015 | Application Cancelled |