Action Date | Action Description |
---|---|
Mar 16, 2010 | Assent Application Received |
Mar 16, 2010 | Administrative Review for Completeness |
Mar 16, 2010 | Team Review for Completeness |
Mar 16, 2010 | Team Review for Completeness |
Mar 19, 2010 | Team Review for Completeness |
Mar 19, 2010 | Team Review for Completeness |
Mar 22, 2010 | Deficient Application - Owner Notification Sent |
Apr 30, 2010 | Deficiency Response Received |
May 04, 2010 | Team Review for Completeness |
May 04, 2010 | Team Review for Completeness |
May 11, 2010 | Application Accepted |
May 13, 2010 | 30 day Public Notice Issued |
May 20, 2010 | HPHC Historical Preservation No Effect |
Jun 02, 2010 | Objections/Comments Received |
Jun 13, 2010 | Public Notice End Date |
Jun 21, 2010 | US Army Corp of Engineers Permit Date |
Jun 25, 2010 | US Army Corps of Engineers Approval Received |
Jul 14, 2010 | Dock Meeting Scheduled (Admin) |
Sep 30, 2010 | Correspondence Received |
Apr 20, 2011 | Engineering Report |
Apr 21, 2011 | Biologist Report |
Apr 22, 2011 | Supervisor Engineer SignOff |
Apr 22, 2011 | Supervisor Biologist SignOff |
Apr 26, 2011 | Executive Signoff of Staff Reports |
Jun 03, 2011 | Ready to Schedule Semi-Monthly Meeting |
Jun 03, 2011 | Mail Agenda Notice |
Jun 07, 2011 | Correspondence Received |
Jun 07, 2011 | Continuance Requested |
Jun 07, 2011 | Entry of Appearance Received |
Jun 08, 2011 | Continuance request by applicant granted by Director |
Jun 08, 2011 | Management Review |
Jun 14, 2011 | Semi-Monthly Meeting Date Scheduled |
Jun 16, 2011 | Dock Subcommittee Meeting Held |
Jun 16, 2011 | Dock Meeting -- Approval |
Jun 22, 2011 | Category A* (Docks) |
Jun 24, 2011 | Permit Approved |
Jun 24, 2011 | Typist for Processing |
Jun 27, 2011 | Executive Sign Off |
Jun 27, 2011 | Sent to Photo Copy |
Jul 05, 2011 | Land Evidence Date |