Action Date | Action Description |
---|---|
Monitoring Report | |
Monitoring Report | |
Mar 26, 2010 | Buffer Zone Management Application Received |
Mar 30, 2010 | Administrative Review for Completeness |
Apr 06, 2010 | Team Review for Completeness |
Apr 06, 2010 | Team Review for Completeness |
Apr 06, 2010 | Application Accepted |
Apr 16, 2010 | HPHC Historical Preservation No Effect |
Aug 19, 2010 | Additional Information Received |
Aug 20, 2010 | Biologist Report |
Aug 20, 2010 | Engineering Report |
Aug 23, 2010 | Typist for Processing |
Aug 23, 2010 | Permit Approved |
Aug 24, 2010 | Executive Sign Off |
Aug 24, 2010 | Sent to Photo Copy |
Aug 31, 2010 | Land Evidence Date |
Nov 10, 2010 | Commencement of Work Notice received |
Jun 07, 2018 | Additional Information Requested from Applicant |
Jun 19, 2018 | Note to File |
Aug 28, 2018 | 30-Day Notification of Cancellation letter |
Sep 17, 2018 | Note to File |
Oct 01, 2018 | Correspondence Mailed/Faxed/E-mailed |
Oct 17, 2018 | Correspondence Received |