Action Date | Action Description |
---|---|
Apr 12, 2010 | Assent Application Received |
Apr 14, 2010 | Administrative Review for Completeness |
Apr 22, 2010 | Team Review for Completeness |
Apr 22, 2010 | Team Review for Completeness |
Apr 22, 2010 | Deficient Application - Owner Notification Sent |
May 10, 2010 | Deficiency Response Received |
May 10, 2010 | Team Review for Completeness |
May 10, 2010 | Team Review for Completeness |
May 10, 2010 | Application Accepted |
May 20, 2010 | HPHC Historical Preservation No Effect |
Jul 01, 2010 | Engineering Report |
Jul 02, 2010 | Plans Received |
Jul 08, 2010 | Typist for Processing |
Jul 08, 2010 | Permit Approved |
Jul 15, 2010 | Land Evidence Date |