Action Date | Action Description |
---|---|
Apr 13, 2010 | Assent Application Received |
Apr 14, 2010 | Administrative Review for Completeness |
Apr 30, 2010 | Team Review for Completeness |
Apr 30, 2010 | Team Review for Completeness |
Apr 30, 2010 | Application Accepted |
May 10, 2010 | HPHC Historical Preservation No Effect |
Jun 08, 2010 | 30 day Public Notice Issued |
Jun 28, 2010 | Objections/Comments Received |
Jul 08, 2010 | Public Notice End Date |
Jul 20, 2010 | US Army Corp of Engineers Permit Date |
Jul 23, 2010 | US Army Corps of Engineers Approval Received |
Jul 29, 2010 | Supervisor Engineer SignOff |
Jul 29, 2010 | Supervisor Biologist SignOff |
Jul 29, 2010 | Biologist Report |
Jul 29, 2010 | Engineering Report |
Aug 06, 2010 | Executive Signoff of Staff Reports |
Aug 27, 2010 | Water Quality Certification |
Aug 27, 2010 | Water Quality Certification |
Aug 31, 2010 | Ready to Schedule Semi-Monthly Meeting |
Sep 01, 2010 | Mail Agenda Notice |
Sep 28, 2010 | Semi-Monthly Meeting Date Scheduled |
Oct 07, 2010 | Mail Agenda Notice |
Oct 12, 2010 | Semi-Monthly Meeting Held |
Oct 12, 2010 | Council Approval Granted |
Oct 13, 2010 | Semi-Monthly Meeting Date Scheduled |
Oct 26, 2010 | Legal Response/Decision |
Nov 12, 2010 | Typist for Processing |
Nov 12, 2010 | Stipulation Package from Biologist |
Nov 12, 2010 | Stipulation Package by Engineer |
Nov 12, 2010 | Permit Approved |
Nov 17, 2010 | Executive Sign Off |
Nov 17, 2010 | Sent to Photo Copy |
Nov 19, 2010 | Land Evidence Date |
May 09, 2011 | Commencement of Work Notice received |