Action Date | Action Description |
---|---|
Apr 22, 2010 | Assent Application Received |
Apr 26, 2010 | Administrative Review for Completeness |
Apr 28, 2010 | Team Review for Completeness |
Apr 28, 2010 | Team Review for Completeness |
Apr 28, 2010 | Additional Information Received |
Apr 28, 2010 | Application Accepted |
May 20, 2010 | HPHC Historical Preservation No Effect |
Jul 21, 2010 | Engineering Report |
Jul 29, 2010 | Permit Approved |
Aug 02, 2010 | Typist for Processing |
Aug 03, 2010 | Executive Sign Off |
Aug 03, 2010 | Sent to Photo Copy |
Nov 26, 2010 | Land Evidence Date |
Apr 20, 2011 | Correspondence Received |
Apr 25, 2011 | Correspondence Mailed/Faxed/E-mailed |
Jan 13, 2014 | Extension Toll letter mailed |
Feb 26, 2014 | Extension of Permit Request |