Action Date | Action Description |
---|---|
Apr 30, 2010 | Assent Application Received |
May 05, 2010 | Administrative Review for Completeness |
May 10, 2010 | Team Review for Completeness |
May 10, 2010 | Team Review for Completeness |
May 10, 2010 | Application Accepted |
May 20, 2010 | HPHC Historical Preservation No Effect |
Jun 07, 2010 | US Army Corp of Engineers Permit Date |
Sep 17, 2010 | Plans Received |
Sep 17, 2010 | Additional Information Received |
Nov 08, 2010 | 30 day Public Notice Issued |
Dec 03, 2010 | Public Notice End Date |
Dec 06, 2010 | Additional Information Received |
Jan 26, 2011 | Correspondence Received |
Jan 27, 2011 | Additional Information Received |
Sep 13, 2012 | Engineering Report |
Sep 20, 2012 | Biologist Report |
Sep 24, 2012 | Executive Signoff of Staff Reports |
Oct 01, 2012 | Ready to Schedule Semi-Monthly Meeting |
Oct 01, 2012 | Mail Agenda Notice |
Oct 23, 2012 | Council Approval Granted |
Oct 23, 2012 | Semi-Monthly Meeting Held |
Oct 23, 2012 | Semi-Monthly Meeting Date Scheduled |
Nov 06, 2012 | Stipulation Package from Biologist |
Nov 06, 2012 | Stipulation Package by Engineer |
Nov 07, 2012 | Typist for Processing |
Nov 07, 2012 | Permit Approved |
Nov 08, 2012 | 30 Day Appeal Notification to Owner |
Nov 08, 2012 | Legal Response/Decision |
Nov 20, 2012 | Executive Sign Off |
Nov 20, 2012 | Sent to Photo Copy |
Nov 30, 2012 | Land Evidence Date |