Action Date | Action Description |
---|---|
May 01, 2012 | Assent Application Received |
May 02, 2012 | Administrative Review for Completeness |
May 02, 2012 | Team Review for Completeness |
May 02, 2012 | Team Review for Completeness |
May 02, 2012 | Application Accepted |
May 04, 2012 | Additional Information Received |
May 07, 2012 | Additional Information Received |
May 11, 2012 | Biologist Report |
May 11, 2012 | Engineering Report |
May 16, 2012 | Typist for Processing |
May 16, 2012 | Executive Sign Off |
May 16, 2012 | Sent to Photo Copy |
May 16, 2012 | Permit Approved |
May 22, 2012 | Land Evidence Date |
Jun 18, 2012 | HPHC Historical Preservation No Effect |
Nov 05, 2014 | Modification Request |
Nov 05, 2014 | Administrative Review for Completeness |
Nov 07, 2014 | Team Review for Completeness |