Action Date | Action Description |
---|---|
Oct 12, 2017 | Assent Application Received |
Oct 13, 2017 | Administrative Review for Completeness |
Oct 13, 2017 | Team Review for Completeness |
Oct 13, 2017 | Application Accepted |
Nov 02, 2017 | HPHC Historical Preservation No Effect |
Nov 15, 2017 | Biologist Report |
Nov 16, 2017 | Typist for Processing |
Nov 16, 2017 | Executive Sign Off |
Nov 16, 2017 | Sent to Photo Copy |
Nov 16, 2017 | Permit Approved |