Action Date | Action Description |
---|---|
Legal Response/Decision | |
Dock Post-Construction Certification by Engineer received. | |
Mar 07, 2019 | Assent Application Received |
Mar 11, 2019 | Administrative Review for Completeness |
Mar 13, 2019 | Team Review for Completeness |
Mar 13, 2019 | Application Accepted |
Mar 13, 2019 | Category A* (Docks) |
Mar 13, 2019 | Category A* (Docks) |
Mar 25, 2019 | 30 day Public Notice Issued |
Mar 29, 2019 | HPHC Review Pending |
Mar 29, 2019 | HPHC Historical Preservation No Effect |
Apr 25, 2019 | Public Notice End Date |
May 02, 2019 | Dock Meeting -- Approval |
Aug 19, 2019 | Additional Information Received |
Aug 21, 2019 | 30 day Public Notice Issued |
Sep 20, 2019 | Public Notice End Date |
Oct 09, 2019 | Biologist Report |
Oct 09, 2019 | Mail Agenda Notice |
Oct 11, 2019 | Supervisor Biologist SignOff |
Oct 11, 2019 | Supervisor Engineer SignOff |
Oct 11, 2019 | Executive Sign Off |
Oct 22, 2019 | Council Approval Granted |
Oct 22, 2019 | Semi-Monthly Meeting Date Scheduled |
Oct 28, 2019 | Stipulation Package from Biologist |
Oct 30, 2019 | Typist for Processing |
Oct 30, 2019 | Executive Sign Off |
Oct 30, 2019 | Sent to Photo Copy |
Oct 30, 2019 | Permit Approved |
Nov 14, 2019 | US Army Corps of Engineers Approval Received |
Jan 21, 2020 | Land Evidence Date |
Mar 02, 2020 | Modification Request |
Mar 03, 2020 | Administrative Review for Completeness |
Mar 13, 2020 | Bio Team Review for Completeness |
Mar 17, 2020 | Project Manager |
Mar 19, 2020 | HPHC Historical Preservation No Effect |
Mar 19, 2020 | HPHC Review Pending |
Mar 27, 2020 | 30 day Public Notice Issued |
Apr 07, 2020 | US Army Corps of Engineers Approval Received |
Apr 21, 2020 | Dock Meeting -- Approval |
Apr 27, 2020 | Public Notice End Date |
May 04, 2020 | Biologist Report |
May 04, 2020 | Engineering Report |
May 04, 2020 | Modification Approved |
Jul 31, 2020 | Land Evidence Date |