Action Date | Action Description |
---|---|
Sep 24, 2019 | Assent Application Received |
Sep 24, 2019 | Administrative Review for Completeness |
Oct 02, 2019 | Plans Received |
Oct 03, 2019 | Bio Team Review for Completeness |
Oct 07, 2019 | Application Accepted |
Nov 07, 2019 | HPHC Review Pending |
Nov 07, 2019 | HPHC Historical Preservation No Effect |
Nov 13, 2019 | Additional Information Received |
Feb 06, 2020 | Additional Information Received |
Feb 14, 2020 | Engineering Report |
Feb 14, 2020 | Biologist Report |
Feb 21, 2020 | Typist for Processing |
Feb 21, 2020 | Executive Sign Off |
Feb 21, 2020 | Sent to Photo Copy |
Feb 21, 2020 | Permit Approved |
Mar 03, 2020 | Land Evidence Date |