Action Date | Action Description |
---|---|
Legal Response/Decision | |
Dock Post-Construction Certification by Engineer received. | |
May 12, 2020 | Assent Application Received |
May 14, 2020 | Administrative Review for Completeness |
May 15, 2020 | Eng Team Review for Completeness |
May 15, 2020 | Bio Team Review for Completeness |
May 15, 2020 | Project Manager |
May 15, 2020 | Application Accepted |
Jun 08, 2020 | Joint Public Notice |
Jun 11, 2020 | HPHC Review Pending |
Jun 11, 2020 | HPHC Historical Preservation No Effect |
Jul 08, 2020 | Public Notice End Date |
Aug 24, 2020 | Comments Received |
Sep 03, 2020 | Water Quality Certification |
Sep 17, 2020 | Engineering Report |
Sep 30, 2020 | Biologist Report |
Sep 30, 2020 | Ready to Schedule Semi-Monthly Meeting |
Sep 30, 2020 | Mail Agenda Notice |
Oct 13, 2020 | Council Approval Granted |
Oct 13, 2020 | Semi-Monthly Meeting Date Scheduled |
Oct 27, 2020 | Typist for Processing |
Oct 27, 2020 | Executive Sign Off |
Oct 27, 2020 | Sent to Photo Copy |
Oct 27, 2020 | Permit Approved |
Oct 27, 2020 | Stipulation Package by Engineer |
Nov 09, 2020 | Land Evidence Date |