Action Date | Action Description |
---|---|
Legal Response/Decision | |
CHA -- application modified due to CHA info | |
Dock Post-Construction Certification by Engineer received. | |
May 21, 2020 | Assent Application Received |
May 21, 2020 | Administrative Review for Completeness |
Jun 08, 2020 | Bio Team Review for Completeness |
Jun 08, 2020 | Project Manager |
Jun 08, 2020 | Application Accepted |
Jun 08, 2020 | Category A* (Docks) |
Jun 11, 2020 | HPHC Historical Preservation No Effect |
Jun 11, 2020 | HPHC Review Pending |
Jul 20, 2020 | Plans Received |
Jul 27, 2020 | 30 day Public Notice Issued |
Aug 24, 2020 | Comments Received |
Aug 26, 2020 | Public Notice End Date |
Sep 17, 2020 | Dock Meeting -- To Council |
Sep 23, 2020 | Biologist Report |
Sep 30, 2020 | US Army Corps of Engineers Approval Received |
Jan 28, 2021 | Ready to Schedule Semi-Monthly Meeting |
Jan 28, 2021 | Mail Agenda Notice |
Feb 09, 2021 | Semi-Monthly Meeting Date Scheduled |
Feb 09, 2021 | Council Approval Granted |
Feb 10, 2021 | Stipulation Package from Biologist |
Feb 10, 2021 | Typist for Processing |
Feb 10, 2021 | Executive Sign Off |
Feb 10, 2021 | Sent to Photo Copy |
Feb 10, 2021 | Permit Approved |
Feb 23, 2021 | Land Evidence Date |