Action Date | Action Description |
---|---|
Feb 17, 2021 | Assent Application Received |
Feb 18, 2021 | Administrative Review for Completeness |
Feb 23, 2021 | Bio Team Review for Completeness |
Feb 23, 2021 | Application Accepted |
Feb 23, 2021 | Project Manager |
Mar 03, 2021 | HPHC Historical Preservation No Effect |
Mar 03, 2021 | HPHC Review Pending |
Apr 02, 2021 | Stipulation Package from Biologist |
Apr 02, 2021 | Biologist Report |
Apr 05, 2021 | Typist for Processing |
Apr 05, 2021 | Executive Sign Off |
Apr 05, 2021 | Sent to Photo Copy |
Apr 05, 2021 | Permit Approved |
Apr 28, 2021 | Land Evidence Date |