Action Date | Action Description |
---|---|
May 14, 2021 | Assent Application Received |
May 17, 2021 | Administrative Review for Completeness |
May 20, 2021 | Eng Team Review for Completeness |
May 20, 2021 | Application Accepted |
May 20, 2021 | Engineering Report |
May 21, 2021 | Stipulation Package by Engineer |
May 21, 2021 | Typist for Processing |
May 21, 2021 | Permit Approved |
Jun 08, 2021 | HPHC Review Pending |
Jun 08, 2021 | HPHC Historical Preservation No Effect |
Sep 16, 2021 | Land Evidence Date |