Dock Post-Construction Certification by Engineer received.
Dec 06, 2021 Assent Application Received
Dec 09, 2021 Administrative Review for Completeness
Dec 09, 2021 Category A* (Docks)
Feb 08, 2022 Bio Team Review for Completeness
Feb 14, 2022 Deficient Application - Owner Notification Sent
May 27, 2022 Deficiency Response Received
Jun 07, 2022 Bio Team Review for Completeness
Jun 07, 2022 Application Accepted
Jun 10, 2022 Project Manager
Jun 21, 2022 HPHC Review Pending
Jun 21, 2022 HPHC Historical Preservation No Effect
Jun 29, 2022 30 day Public Notice Issued
Jul 01, 2022 US Army Corps of Engineers Approval Received
Jul 29, 2022 Public Notice End Date
Aug 17, 2022 Dock Meeting -- Approval
Aug 19, 2022 Biologist Report
Aug 23, 2022 Typist for Processing
Aug 23, 2022 Executive Sign Off
Aug 23, 2022 Sent to Photo Copy
Aug 23, 2022 Permit Approved
Aug 23, 2022 Permit Mailed
Jan 11, 2023 Land Evidence Date

Details:

File No
2021-12-013
Town
Narragansett
First Name
Cedar Point LLC
Last Name
Street
- 101B Kenyon Farms Road
Location
101A - 101B Kenyon Farms Road
Plat/Map
Y-4
Lot/Block
1A
Decision Date
Aug 23, 2022
Dock Reg.No
2475
Project
c/m a residential boating facility
Description
Docks, Piers, Floats (Residential)
Water Area
Point Judith Pond (Narragansett)
Easement
0
Acceptance Date
Jun 07, 2022