Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 06, 2021 | Assent Application Received |
Dec 09, 2021 | Administrative Review for Completeness |
Dec 09, 2021 | Category A* (Docks) |
Feb 08, 2022 | Bio Team Review for Completeness |
Feb 14, 2022 | Deficient Application - Owner Notification Sent |
May 27, 2022 | Deficiency Response Received |
Jun 07, 2022 | Bio Team Review for Completeness |
Jun 07, 2022 | Application Accepted |
Jun 10, 2022 | Project Manager |
Jun 21, 2022 | HPHC Review Pending |
Jun 21, 2022 | HPHC Historical Preservation No Effect |
Jun 29, 2022 | 30 day Public Notice Issued |
Jul 01, 2022 | US Army Corps of Engineers Approval Received |
Jul 29, 2022 | Public Notice End Date |
Aug 17, 2022 | Dock Meeting -- Approval |
Aug 19, 2022 | Biologist Report |
Aug 23, 2022 | Typist for Processing |
Aug 23, 2022 | Executive Sign Off |
Aug 23, 2022 | Sent to Photo Copy |
Aug 23, 2022 | Permit Approved |
Aug 23, 2022 | Permit Mailed |
Jan 11, 2023 | Land Evidence Date |