Action Date | Action Description |
---|---|
Jan 04, 2022 | Assent Application Received |
Jan 07, 2022 | Administrative Review for Completeness |
Jan 07, 2022 | CHA Worksheet received |
Jan 12, 2022 | Bio Team Review for Completeness |
Jan 24, 2022 | Application Accepted |
Jan 24, 2022 | Project Manager |
Jan 31, 2022 | Category B assigned |
Feb 21, 2022 | 30 day Public Notice Issued |
Feb 25, 2022 | HPHC Review Pending |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Mar 18, 2022 | Objections/Comments Received |
Mar 21, 2022 | Objections/Comments Received |
Mar 21, 2022 | Public Notice End Date |
Aug 03, 2022 | Public Hearing Notices Mailed |
Aug 17, 2022 | Engineering Report |
Aug 17, 2022 | Supervisor Engineer SignOff |
Aug 17, 2022 | Supervisor Biologist SignOff |
Aug 18, 2022 | Executive Signoff of Staff Reports |
Aug 23, 2022 | Council Approval Granted |
Aug 23, 2022 | Semi-Monthly Meeting Date Scheduled |
Oct 18, 2022 | Plans Received |
Nov 14, 2022 | Stipulation Package by Engineer |
Nov 15, 2022 | Legal Response/Decision |
Nov 15, 2022 | 30 Day Appeal Notification to Owner |
Jan 26, 2023 | Typist for Processing |
Jan 26, 2023 | Executive Sign Off |
Jan 26, 2023 | Sent to Photo Copy |
Jan 26, 2023 | Permit Approved |
Jan 27, 2023 | Permit Mailed |
Feb 13, 2023 | Land Evidence Date |