Action Date | Action Description |
---|---|
Nov 15, 2022 | Freshwater Wetlands Application - New - received |
Nov 18, 2022 | Administrative Review for Completeness |
Dec 01, 2022 | Bio Team Review for Completeness |
Dec 01, 2022 | Application Accepted |
Dec 01, 2022 | Project Manager |
Jan 03, 2023 | HPHC Historical Preservation No Effect |
Jan 12, 2023 | Biologist Report |
Jan 19, 2023 | Typist for Processing |
Jan 19, 2023 | Executive Sign Off |
Jan 19, 2023 | Sent to Photo Copy |
Jan 19, 2023 | Permit Approved |
Jan 20, 2023 | Permit Mailed |
Jan 27, 2023 | Land Evidence Date |