Action Date | Action Description |
---|---|
Jan 25, 2023 | Assent Application Received |
Jan 27, 2023 | Administrative Review for Completeness |
Jan 31, 2023 | Bio Team Review for Completeness |
Jan 31, 2023 | Project Manager |
Jan 31, 2023 | Application Accepted |
Feb 13, 2023 | 30 day Public Notice Issued |
Feb 15, 2023 | HPHC Historical Preservation No Effect |
Mar 14, 2023 | Public Notice End Date |
Apr 06, 2023 | Dock Meeting -- Approval |
Apr 07, 2023 | Biologist Report |
May 08, 2023 | Typist for Processing |
May 08, 2023 | Executive Sign Off |
May 08, 2023 | Sent to Photo Copy |
May 08, 2023 | Permit Approved |
May 09, 2023 | Land Evidence Date |
Jul 27, 2023 | Commencement of Work Notice received |