Action Date | Action Description |
---|---|
Jan 30, 2023 | Maintenance Certification Request |
Jan 31, 2023 | Administrative Review for Completeness |
Feb 08, 2023 | Eng Team Review for Completeness |
Feb 08, 2023 | Project Manager |
Feb 08, 2023 | Application Accepted |
Feb 17, 2023 | HPHC Historical Preservation No Effect |
Mar 06, 2023 | Engineering Report |
Mar 15, 2023 | HPHC Historical Preservation No Effect |
Mar 23, 2023 | Typist for Processing |
Mar 23, 2023 | Permit Approved |
Mar 27, 2023 | Land Evidence Date |
Mar 27, 2023 | Commencement of Work Notice received |