Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 09, 2023 | Assent Application Received |
Feb 15, 2023 | Administrative Review for Completeness |
Feb 15, 2023 | Bio Team Review for Completeness |
Feb 15, 2023 | Application Accepted |
Feb 17, 2023 | Project Manager |
Feb 17, 2023 | Category A* (Docks) |
Feb 22, 2023 | 30 day Public Notice Issued |
Feb 28, 2023 | HPHC Historical Preservation No Effect |
Mar 24, 2023 | Public Notice End Date |
May 11, 2023 | Dock Meeting -- Approval |
Jun 22, 2023 | Additional Information Received |
Jul 27, 2023 | Plans Received |
Aug 01, 2023 | Biologist Report |
Aug 04, 2023 | Typist for Processing |
Aug 08, 2023 | Executive Sign Off |
Aug 08, 2023 | Sent to Photo Copy |
Aug 08, 2023 | Permit Approved |
Aug 09, 2023 | Permit Mailed |
Aug 16, 2023 | Land Evidence Date |