Action Date | Action Description |
---|---|
Assent Requirement | |
Feb 13, 2023 | CHA Worksheet received |
Feb 13, 2023 | Assent Application Received |
Feb 17, 2023 | Administrative Review for Completeness |
Feb 20, 2023 | Bio Team Review for Completeness |
Feb 20, 2023 | Project Manager |
Feb 20, 2023 | Application Accepted |
Mar 20, 2023 | Additional Information Received |
Apr 26, 2023 | HPHC Historical Preservation Comments/Concerns |
Aug 22, 2023 | Additional Information Received |
Oct 04, 2023 | 30 day Public Notice Issued |
Oct 16, 2023 | Comments Received |
Nov 01, 2023 | Comments Received |
Nov 04, 2023 | Public Notice End Date |
Nov 14, 2023 | Letter of Support for Project |
Dec 04, 2023 | Additional Information Received |
Dec 11, 2023 | Additional Information Received |
Mar 12, 2024 | Additional Information Received |
May 08, 2024 | Biologist Report |
May 08, 2024 | HPHC Review Pending |
May 21, 2024 | Engineering Report |
May 28, 2024 | Typist for Processing |
May 28, 2024 | Permit Approved |
May 29, 2024 | Executive Sign Off |
May 29, 2024 | Permit Mailed |
Jun 06, 2024 | Land Evidence Date |