Action Date | Action Description |
---|---|
Feb 15, 2023 | Assent Application Received |
Feb 22, 2023 | Administrative Review for Completeness |
Feb 23, 2023 | Eng Team Review for Completeness |
Feb 23, 2023 | Project Manager |
Feb 23, 2023 | Application Accepted |
Mar 24, 2023 | HPHC Historical Preservation No Effect |
Jul 19, 2023 | Plans Received |
Jul 28, 2023 | Typist for Processing |
Jul 28, 2023 | Executive Sign Off |
Jul 28, 2023 | Sent to Photo Copy |
Jul 28, 2023 | Permit Approved |
Jul 28, 2023 | Engineering Report |