Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 17, 2023 | Assent Application Received |
Feb 23, 2023 | Administrative Review for Completeness |
Mar 01, 2023 | Bio Team Review for Completeness |
Mar 01, 2023 | Application Accepted |
Mar 01, 2023 | Project Manager |
Mar 15, 2023 | HPHC Historical Preservation No Effect |
Apr 27, 2023 | Additional Information Received |
May 16, 2023 | 30 day Public Notice Issued |
Jun 16, 2023 | Public Notice End Date |
Jul 16, 2023 | Public Notice End Date Extension Granted |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Sep 25, 2023 | Plans Received |
Oct 02, 2023 | Biologist Report |
Oct 03, 2023 | Typist for Processing |
Oct 03, 2023 | Executive Sign Off |
Oct 03, 2023 | Sent to Photo Copy |
Oct 03, 2023 | Permit Approved |
Oct 05, 2023 | Permit Mailed |
Nov 06, 2023 | Land Evidence Date |