Action Date | Action Description |
---|---|
Feb 24, 2023 | Buffer Zone Management Application Received |
Mar 01, 2023 | Administrative Review for Completeness |
Mar 01, 2023 | Bio Team Review for Completeness |
Mar 01, 2023 | Application Accepted |
Mar 01, 2023 | Project Manager |
Mar 15, 2023 | HPHC Historical Preservation No Effect |
Apr 26, 2023 | Biologist Report |
May 03, 2023 | Typist for Processing |
May 03, 2023 | Executive Sign Off |
May 03, 2023 | Sent to Photo Copy |
May 03, 2023 | Permit Approved |
May 05, 2023 | Permit Mailed |
May 31, 2023 | Land Evidence Date |
Oct 03, 2023 | Commencement of Work Notice received |