Action Date | Action Description |
---|---|
Mar 10, 2023 | Buffer Zone Management Application Received |
Mar 14, 2023 | Administrative Review for Completeness |
Mar 14, 2023 | Bio Team Review for Completeness |
Mar 14, 2023 | Project Manager |
Mar 14, 2023 | Application Accepted |
Mar 22, 2023 | HPHC Historical Preservation No Effect |
Mar 29, 2023 | Biologist Report |
Apr 19, 2023 | Typist for Processing |
Apr 19, 2023 | Executive Sign Off |
Apr 19, 2023 | Sent to Photo Copy |
Apr 19, 2023 | Permit Approved |
Apr 24, 2023 | Permit Mailed |
Apr 28, 2023 | Commencement of Work Notice received |
May 10, 2023 | Assent Requirement |