Action Date | Action Description |
---|---|
Apr 11, 2023 | Assent Application Received |
Apr 13, 2023 | Administrative Review for Completeness |
Apr 21, 2023 | Bio Team Review for Completeness |
Apr 25, 2023 | Application Accepted |
Apr 25, 2023 | Project Manager |
Apr 25, 2023 | Eng Team Review for Completeness |
May 04, 2023 | HPHC Historical Preservation No Effect |
May 26, 2023 | 30 day Public Notice Issued |
Jun 26, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Aug 14, 2023 | Engineering Report |
Aug 22, 2023 | Permit Mailed |
Aug 22, 2023 | Typist for Processing |
Aug 22, 2023 | Executive Sign Off |
Aug 22, 2023 | Sent to Photo Copy |
Aug 22, 2023 | Permit Approved |
Oct 17, 2023 | Commencement of Work Notice received |
Oct 03, 2024 | Land Evidence Date |