Action Date | Action Description |
---|---|
May 02, 2023 | Assent Application Received |
May 08, 2023 | Administrative Review for Completeness |
May 09, 2023 | Bio Team Review for Completeness |
May 09, 2023 | Project Manager |
May 09, 2023 | Application Accepted |
Jun 05, 2023 | HPHC Historical Preservation No Effect |
Jul 31, 2023 | Plans Received |
Aug 02, 2023 | Biologist Report |
Aug 04, 2023 | Typist for Processing |
Aug 04, 2023 | Executive Sign Off |
Aug 04, 2023 | Sent to Photo Copy |
Aug 04, 2023 | Permit Approved |
Aug 09, 2023 | Permit Mailed |
Oct 02, 2023 | Land Evidence Date |