Action Date | Action Description |
---|---|
May 23, 2023 | HPHC Historical Preservation No Effect |
May 23, 2023 | Dredge Application |
May 25, 2023 | Administrative Review for Completeness |
Jun 16, 2023 | Eng Team Review for Completeness |
Jun 16, 2023 | Additional Information Received |
Jun 16, 2023 | Application Accepted |
Jun 16, 2023 | Project Manager |
Jun 16, 2023 | HPHC Historical Preservation No Effect |
Aug 18, 2023 | Correspondence Received |
Nov 06, 2023 | 15 day Public Notice Issued |
Nov 21, 2023 | Public Notice End Date |
Nov 30, 2023 | Engineering Report |
Dec 07, 2023 | Typist for Processing |
Dec 07, 2023 | Executive Sign Off |
Dec 07, 2023 | Sent to Photo Copy |
Dec 07, 2023 | Permit Approved |
Dec 08, 2023 | Permit Mailed |
May 15, 2024 | Land Evidence Date |
Oct 22, 2024 | Commencement of Work Notice received |