Action Date | Action Description |
---|---|
Monitoring Report | |
Jun 16, 2023 | Assent Application Received |
Jun 21, 2023 | Administrative Review for Completeness |
Jun 21, 2023 | Bio Team Review for Completeness |
Jun 21, 2023 | Application Accepted |
Jun 21, 2023 | Project Manager |
Jun 23, 2023 | HPHC Historical Preservation No Effect |
Aug 25, 2023 | Biologist Report |
Aug 28, 2023 | Typist for Processing |
Aug 28, 2023 | Executive Sign Off |
Aug 28, 2023 | Sent to Photo Copy |
Aug 28, 2023 | Permit Approved |
Aug 29, 2023 | Permit Mailed |
Sep 14, 2023 | Assent Amended |
Sep 09, 2024 | US Army Corps of Engineers Approval Received |
Oct 28, 2024 | Commencement of Work Notice received |