Action Date | Action Description |
---|---|
Jul 19, 2023 | Maintenance Certification Request |
Jul 26, 2023 | Administrative Review for Completeness |
Jul 31, 2023 | Eng Team Review for Completeness |
Jul 31, 2023 | Deficient Application - Owner Notification Sent |
Aug 04, 2023 | Deficient Application Picked Up |
Aug 07, 2023 | Deficiency Response Received |
Aug 11, 2023 | Eng Team Review for Completeness |
Aug 11, 2023 | Application Accepted |
Aug 11, 2023 | Project Manager |
Aug 16, 2023 | Engineering Report |
Aug 21, 2023 | Typist for Processing |
Aug 21, 2023 | Executive Sign Off |
Aug 21, 2023 | Sent to Photo Copy |
Aug 21, 2023 | Permit Approved |
Aug 25, 2023 | Permit Mailed |
Aug 25, 2023 | HPHC Historical Preservation No Effect |
Sep 12, 2023 | Commencement of Work Notice received |
Oct 02, 2023 | Land Evidence Date |