Action Date | Action Description |
---|---|
Jul 25, 2023 | Assent Application Received |
Jul 27, 2023 | Administrative Review for Completeness |
Aug 02, 2023 | Bio Team Review for Completeness |
Aug 02, 2023 | Application Accepted |
Aug 02, 2023 | Project Manager |
Aug 04, 2023 | HPHC Historical Preservation No Effect |
Sep 11, 2023 | Biologist Report |
Sep 14, 2023 | Typist for Processing |
Sep 14, 2023 | Executive Sign Off |
Sep 14, 2023 | Sent to Photo Copy |
Sep 18, 2023 | Permit Approved |
Sep 19, 2023 | Permit Mailed |
Sep 27, 2023 | Land Evidence Date |
Oct 17, 2023 | Additional Information Received |
Oct 17, 2023 | Assent Requirement |